In July, slab pours to Level 4 were completed. The formwork is underway for Levels 5 and 6, in preparation for slab pours in August.
Welcome to the July construction update. Traders In Purple is pleased to share the following update regarding construction progress at Orilla.
In July, slab pours to Level 4 were completed. The formwork is underway for Levels 5 and 6, in preparation for slab pours in August. On Level 1,installation of the party walls is almost complete. High level services rough-in on Ground Level and Level 1 is 75% complete. The formwork back propping has been stripped up to Level 2. The people and materials hoist was installed at the rear of the site and the mobile satellite concrete pump is operational.
Looking ahead to August, the construction team anticipate Level 5and6slabs will be poured. Level 1 apartments will start coming together with internal wall and ceiling framing. Level 2 wall framing will also commence.